US equities have often performed well in the year after a midterm election. Capital Group calculates that the S&P 500 rose an average of 15.4% in the 12 months following midterms since 1950, based on price returns through 2025.1 That history offers context, not a forecast: each observation combines an election with its own earnings cycle, monetary conditions and starting valuations.
This election also arrives in the middle of an unusually large infrastructure expansion. The companies building AI capacity need land, power, permits and time before new computing facilities can earn a return. Democratic gains in Congress and in state elections have put fresh attention on how that expansion is approved and who pays for it.
The election changes who can influence the buildout
Democrats are projected to control both chambers of the next Congress, which takes office in January 2027, while President Trump retains the power to veto legislation.2 That makes sweeping federal legislation difficult without agreement across party lines. Congress can still investigate companies and shape negotiations, while executive agencies retain authority under existing law.
For a data-centre developer, the more immediate decisions may be closer to the proposed site. State agencies oversee permits and utility matters, and local governments can influence zoning and development approvals. Their decisions can affect when a project opens, how much infrastructure its owner must fund and whether a site remains viable.
Democrats do not have one uniform approach to the issue. Some support temporary pauses; others want projects to proceed under stricter conditions. Community opposition and concern over household electricity bills also cross party lines.3
Pauses and conditions are already in place
In July 2026, New York Governor Kathy Hochul ordered a pause on specified state environmental permit applications for covered data centres while the state prepares an environmental assessment.4 The order applies to facilities meeting its definition, including an energy threshold of at least 50 megawatts, and to certain applications not deemed complete before the order. It does not halt every project or replace local permitting decisions.
Pennsylvania has taken another route. Governor Josh Shapiro directed changes to the state permit process and removed data-centre proposals from fast-track permitting. His administration's requirements address energy affordability, environmental protection, community engagement and workforce benefits.5 Projects can still move forward, but developers face conditions that may affect cost and timing.
In Ohio, governor-elect Amy Acton campaigned on a conditional moratorium for projects that do not meet requirements on utility costs, labour, transparency and environmental standards.67 That remains a campaign position; its implementation and application to individual projects are yet to be determined.
At the federal level, Senator Bernie Sanders and Representative Alexandria Ocasio-Cortez have proposed a moratorium on AI data centres until federal safeguards are enacted. The Senate bill was introduced and referred to committee; it has not become law.8 Its existence does not establish a party-wide position or the agenda of a future president.
Power changes the cost of growth
Large data centres need electricity, and communities have raised concerns about their effect on household bills.3
Supplying a large new load can require generation, transmission and distribution investment before a facility is operating at full capacity. If a project is delayed or cancelled, some of that infrastructure may be underused. Regulators and communities therefore have reason to ask developers to fund upgrades, provide financial security or accept conditions on electricity use.
The allocation of infrastructure costs can affect a project's return.
Those conditions can improve public accountability without ending development. They can also raise the capital required for a project, lengthen approval, or shift investment towards sites with available power. The effect will vary with the rules, the project and the agreements between developers, utilities and customers.
Capital commitments still need a path to returns
The companies financing the buildout have already set large spending plans. In their third-quarter disclosures, Alphabet guided to USD 195 billion to USD 205 billion of 2026 capital expenditure; Amazon expected approximately USD 220 billion of cash capital expenditure; and Meta expected USD 135 billion to USD 145 billion, including principal payments on finance leases.91011 These are global, company-wide figures with different definitions, not a measure of US data-centre construction alone.
Company-stated CapEx guidance from the 2026 earnings season
USD billions; company-stated periods and definitions
FY2026 · CapEx guidance
Amazon · Amazon, Third quarter 2026 results
approximately 220Calendar 2026 · Cash CapEx guidance
FY2026 · CapEx guidance including finance-lease principal
These are global, company-wide figures with different definitions, not a measure of US data-centre construction alone.
A later opening can delay revenue while financing and construction costs continue. Requiring developers to fund more power infrastructure can also change project economics. Against that, companies may secure power through long-term agreements, redesign projects or move capacity elsewhere. Existing powered facilities could benefit from slower new supply if demand remains strong and operators can capture better economics; that outcome is not automatic.
A future Democratic administration could revise federal priorities and use powers available under existing law, particularly where federal permits or land are involved. Its approach would depend on the president, Congress, the agencies and the courts. A presidential order would not by itself rewrite every statute or control every privately built facility.
The next test is project execution
Investors assessing AI infrastructure should distinguish announced capacity from projects with permits, power agreements and a credible construction timetable. They should also examine who funds grid upgrades, how contracts allocate delays and costs, and when a facility is expected to convert demand into cash.
Footnotes
-
Capital Group, Markets and midterm elections. ↩
-
Pictet, US midterms: a big blue wave. ↩
-
Brookings Institution, Data center moratoriums are not a substitute for oversight. ↩ 2
-
New York State, Executive Order No. 62. ↩
-
Commonwealth of Pennsylvania, Governor Shapiro signs executive order on data center development. ↩
-
Amy Acton for Governor, Support for conditional moratorium on data centers. ↩
-
Ohio Capital Journal, Democrat Amy Acton wins race for Ohio governor. ↩
-
Congress.gov, S.4214: Artificial Intelligence Data Center Moratorium Act. ↩
-
Alphabet, 2026 Q3 earnings call. ↩
-
Amazon, Third quarter 2026 results. ↩
-
Meta, Third quarter 2026 results. ↩